What was the objective of this project?
Transport 24 of the longest turbine blades in North America at 80m in length these blades overhang most suitable inland barges, we engineered administrative controls on towage with movement restrictions and report requirements led to a safe delivery during historic low water
What did SEA.O.G Offshore contribute to this project?
Engineering Services, Field Execution, Barge Prep and Sea Fastening, Marine Contracting, Marine Coordination/weather routing, transload operations, and management
Where did this project take place?
LA/Mid West
What was the timeline on this project?
Transload complete